Tentative Construction Schedule

A bit of good news—the lowering of the lake is scheduled to start after July 4th. Hopefully that will allow you some time to enjoy the lake during upcoming hot spell.

The next phase of construction reroutes the water main. It currently runs under Highland Drive and through the dam. It will be rerouted down the ravine and back up via directional boring.

The contractor will also be working on putting the infrastructure in place to dewater the lake and erosion control measures to mitigate downstream effects.